FIPS 199 High Impact (for ICS) |
| Findings
Color Code |
| Satisfied |
| Other Than Satisfied - not assessed |
| Other Than Satisfied - failed
|
|
|
NIST SP 800-53A PE-10 .01(ii)
|
Question: Does an examination of the emergency shutoff controls or switches confirm that the organization provides for specific locations within a facility containing concentrations of information system resources, the capability of shutting off power to any information system component that may be malfunctioning or threatened without endangering personnel by requiring them to approach the equipment ? |
|
Answered by: BOSTON::JEFFERSON
As part of Manual Examination group: FACILITY
|
Answer: YES
|
|
|
This NIST 800-53 report is posted on the Internet to promote Version 3.0 of LJK/Security . The corresponding vulnerability report for your own system should be guarded more carefully, such as by being reviewed only from local HTML disk files rather than via a web server.
|